Roundabout construction works

16 March, 2021

Wingecarribee Shire Council wishes to advise that roundabout construction works are scheduled to commence at the intersection of Bundaroo and Bendooley Streets in Bowral from Thursday 18 March 2021.

Works will include reconstruction of the existing road pavement including kerb and gutter renewal works and the construction of a reinforced concrete roundabout.

Construction works will be completed in two phases to minimise disruption:

  • Phase one – Trachyte stone kerb and gutter renewal
  • Phase two – Reinforced concrete roundabout, pathway construction and road pavement reconstruction.

Phase one works are scheduled to commence on 18 March and are expected to finish later that month.

Phase two roundabout construction and road works are expected to be carried out during the Easter School Holiday period.

Construction activities will be carried out between 7am and 6pm weekdays.

During construction, sections of the road may be temporarily reduced to one-way traffic. The road will remain open to through traffic with property access being maintained.

Road users are cautioned to follow the changed traffic conditions, including changes to drop off locations for school children, exercise care when travelling through the work zones and be aware of loose stones and heavy machinery within the work areas.

Council thanks residents and motorists in advance for their cooperation and apologises for any temporary delays or inconvenience.

Works are expected to be completed by mid-April 2021.  All timeframes are subject to weather conditions.

For further information please contact Jamil Ashraf from Council’s Infrastructure Services Branch on 4868 0888.