Changed traffic conditions on Kirkham Road, Bowral

14 October, 2019

Wingecarribee Shire Council wishes to advise that utility service relocation works on Kirkham Road in Bowral are scheduled to commence on 21 October 2019.

These works will be carried out along Kirkham Road between Sherwood Ave and Oxleys Hill Road and up to Kiama Street as part of the Kirkham Road (South) Road Reconstruction Project.

The objectives of the overall project include road reconstruction, formalising car parking arrangements and improving pedestrian access.

The scope of the utility service relocation work includes:

  • construction of new stormwater drainage and relocation of existing water main at Sherwood Avenue,
  • relocation of existing gas main at Sherwood Avenue and Wingecarribee Streets, and
  • relocation of existing Telstra and NBN services throughout the project location.

Construction activities will be carried out between 7 am and 6 pm weekdays.

During construction, sections of the road may be temporarily reduced to one-way traffic however property access will be maintained. Prior to works commencing affected properties will be provided with written notification.

Road users are cautioned to follow directions for the changed traffic conditions, exercise care when traveling through the work zones and be aware of loose stones and heavy machinery within the work areas.

Council thanks motorists and pedestrians in advance for their cooperation and apologies for any temporary delays or inconvenience.

Works are expected to be completed by the end of December 2019.  All timeframes are subject to weather conditions.

For further information please contact Jamil Ashraf from Council’s Infrastructure Services Branch on 4868 0888.