Changed traffic conditions – Bundanoon Road, Exeter

5 October, 2018

Wingecarribee Shire Council wishes to advise that road works scheduled for Bundanoon Road in Exeter have been rescheduled to commence from Monday 8 October 2018.

Works will include widening of road shoulders, rehabilitation of the bitumen pavement and pruning of tree branches to improve the sight-line of motorists.  New road signs and line-marking will also be installed.

The work is stage two of the Exeter Black Spot Safety Improvement Project funded by the Australian Government Black Spot Program.

These works will be carried out from the railway overbridge for approximately 170 metres south towards Bundanoon.

Construction activities will be carried out between 7.00am and 6.00pm weekdays.

During construction sections of the road may be temporarily reduced to one-way traffic however the road will remain open to through traffic.

Road users are cautioned to follow the changed traffic conditions, exercise care when traveling through the work zones and be aware of loose stones and heavy machinery within the work areas.

Council thanks residents and motorists in advance for their cooperation and apologises for any temporary delays or inconvenience.

Works are expected to be completed by late November 2018.  All timeframes are subject to weather conditions.

For further information please contact Jamil Ashraf from Council’s Infrastructure Services Branch on 4868 0519.